This guide explains what coordination drawings contain, who prepares and approves them, and what a contractor should expect to receive.
What Are MEP Coordination Drawings?
Coordination drawings, also called combined services drawings, bring every MEP system together on a single architectural and structural background. Their job is to prove that each service has a defined route and level, and that it clears the other services as well as the beams, columns, and ceilings.
They are usually produced during construction, after the design is approved, and they often develop in parallel with each trade's shop drawings rather than always ahead of them. On BIM projects, they are typically extracted from a federated model after clash detection rather than built by overlaying 2D drawings.
What a Coordination Drawing Set Contains
- Combined plans for each floor, showing ducts, pipes, cable trays, and fire protection mains, color-coded by system.
- Sections through congested areas, showing how the services stack and the level of each one, referenced to the slab or the finished floor level.
- Ceiling void depths and the clearances needed for insulation, hangers, and maintenance access.
- Openings and sleeves in slabs, walls, and beams. No opening in a structural element is approved without the structural engineer's agreement.
- Ceiling coordination: diffusers, light fixtures, sprinkler heads, detectors, and access panels.
- Notes on issues that need a decision from the designer, raised as requests for information (RFIs).
3D MEP Coordinated Drawings
On BIM projects the coordination is done in a 3D model, and the drawings are views of that coordinated model rather than sheets drafted one by one. This is what "3D MEP coordinated drawings" usually refers to. They typically add the following to the set:
- Plans and sections cut from the federated model itself, so the sheets follow the model when a route or level changes, and are checked again before they are reissued.
- 3D or isometric views of congested areas, such as corridor junctions, risers, and plant rooms, where a plan and a section alone do not make the stacking clear.
- Views color-coded or filtered by system, showing one trade against the background of the others.
The 3D views help the site team read the arrangement. Installation still works from the dimensioned plans and sections, with their levels, unless the project specifications say otherwise. How much is modeled, and to which level of development, such as LOD 350 or LOD 400, is set by the BIM execution plan and the contract. For modeling and clash detection, see our BIM services.
Who Prepares Them and Who Approves Them
The contract documents define the responsibilities. A common arrangement on Gulf projects looks like this:
- The MEP contractor or main contractor prepares the coordination drawings, either in-house or through a specialist engineering office working on its behalf.
- The main contractor carries overall responsibility for coordinating the subcontractors with one another and with the architectural and structural works.
- The supervision consultant reviews the drawings and approves them or returns them with comments, following the project's submittal procedure.
- The designer is consulted when resolving a clash means changing a size or route that affects the design intent.
The consultant's approval does not relieve the contractor of responsibility for coordination unless the contract says otherwise.
Coordination Drawings vs. Shop Drawings
The two are often confused, but they answer different questions:
- A coordination drawing asks: does everything fit? It shows all trades together and focuses on routes, levels, and clearances.
- A shop drawing asks: how exactly is this system installed? It covers one trade and shows sizes, fittings, supports, installation details, and approved materials.
The two do not always run in sequence. On many projects they develop in parallel: congested areas are settled in coordination first, each trade's drawings move ahead elsewhere, and both are updated after every coordination round. What matters is that no shop drawing is issued for installation in an area whose coordination is still open, because that invites rework on site.
Where Clashes Concentrate: Corridors, Risers, and Plant Rooms
- Corridors: Main ducts, chilled-water pipes, fire mains, and cable trays share a limited ceiling void, squeezed further by drop beams. The team agrees on a stacking order. A common starting point is to fix the gravity drainage route first, because its slope is the hardest to adjust, but that priority is not absolute: the final order depends on project conditions such as main duct sizes, the required clear height, and maintenance access.
- Risers: Check the spacing between pipes once insulation is added, access to valves, slab opening sizes once the structural engineer has approved them, and firestopping.
- Plant rooms: Check maintenance clearances around equipment, the space needed to pull coils and filters, plinths, and the route for bringing equipment in and out.
Ceilings above toilets and kitchens, and basements where parking headroom governs, deserve the same attention.
What the Contractor Receives
The contract documents define what is delivered. Depending on the scope, the package may include:
- Coordinated floor plans, with sections and enlarged details of congested areas.
- Builder's work drawings showing openings and sleeves, once the structural engineer has approved the structural openings.
- A clash report and a log of how each clash was resolved, where the contract calls for them.
- The federated model, where its handover is part of the contract, with DWG and PDF sheets as the project requires.
- A list of open RFIs.
At Al Abbas Engineering Consultants, we prepare this package remotely for contractors and consultants in Saudi Arabia, the UAE, and the wider Gulf. Formal submissions to the authorities are made by the locally licensed party.
Frequently Asked Questions
Are coordination drawings required on every project?
They are required when the project specifications or the consultant's procedures call for them, which is common on medium and large projects. Even where they are not formally required, coordinating the congested areas saves the contractor rework.
Does a BIM model replace coordination drawings?
The model is the coordination tool, but the site team and the consultant usually still need drawings extracted from it, with levels, sections, and an approval status. The contract defines what must be delivered.
What scale are coordination drawings drawn at?
There is no fixed scale. Common examples are 1:50 for plans and a larger scale such as 1:20 for sections and details, but these are examples, not requirements. The project specifications, the size of the area, and how congested it is decide.
Who resolves a clash that requires a design change?
The contractor raises an RFI to the consultant with a proposed solution. A change that affects sizes or performance goes ahead only after the designer agrees.